The next steps for the mega-line that will deliver cheaper energy

The project received a recommendation for approval of its environmental permit. Now, the SEA management must issue the RCA.

The Kimal-Lo Aguirre transmission line, which will connect the Antofagasta Region with the Metropolitan Region, is one step closer to construction. The US$1.5 billion investment will help transport renewable energy produced in northern Chile to the center of the country, which in the long term will contribute to lower energy prices.

Kimal–Lo Aguirre HVDC line project in final stages for environmental approval following SEA recommendation

The Environmental Assessment Service (SEA) submitted the Consolidated Assessment Report on the Environmental Impact Study for the “Kimal-Lo Aguirre HVDC Power Transmission Line” project, recommending the approval of this megaproject that aims to connect the Antofagasta region with the Metropolitan region using high-voltage direct current (HVDC) technology, with a route of 1,346 kilometers and an estimated investment of US$1.48 billion.